Axiom Management & Engineering, Inc. |
Trinity Railway Express
Euless South Main Bridge
Replacement
During this project Axiom M&E Provided the following services:
-
Construction Management
-
Railroad Engineering
-
Contract Administration
-
On-Site Observation
-
Storm Water Management
|

Click to Enlarge |
|
This project consisted of the replacement of dual twin timber
railroad bridges that was burned by arson. This bridge remained in service while the
adjacent bridge was replaced.
|
|
The bridges carried over 40
trains (passenger and freight) a day. The new bridges were 196 feet long
and consisted of steel pile and precast caps and beams. |

Click to Enlarge
|
|
It was determined that one of the bridges was structurally sufficient
to carry the train loading. Upon completion the other bridge was
removed from service and replaced. |

Click to Enlarge |
Contact us for more info
|

|